![]() |
THE RESTORATION UPDATED DECEMBER 20, 2017 * HIT YOUR BROWSER'S REFRESH BUTTON TO SEE THE LATEST ADDITIONS |
FOLLOW THE PROGRESS OF THE P-61 RESTORATION THROUGH THIS PHOTOGRAPHIC CHRONOLOGY * IF YOU ARE A RETURNING VISITOR AND WISH TO SEE ONLY THE LATEST PROGRESS PHOTOS, CLICK HERE. |
|
|
|
OCTOBER 6, 1991 |
![]()
OCTOBER 6, 1991 |
|
|
OCTOBER 6, 1991 |
![]() DECEMBER 15, 1992 |
|
|
DECEMBER 12, 1992 |
DECEMBER 15, 1992 |
|
|
![]() JULY 24, 1994 |
![]() JULY 24, 1994 |
|
|
JULY 25, 1994 |
SEPTEMBER 7, 1994 |
MARCH 24, 1996 |
JUNE 2, 1996 |
NOVEMBER 10, 1997 |
JANUARY 12, 1998 |
JANUARY 12, 1998 |
JANUARY 12, 1998 |
|
|
OCTOBER 11, 1998 |
|
|
|
OCTOBER 11, 1998 |
JUNE 7, 1999 |
|
|
JUNE 7, 1999 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
FEBRUARY 15, 2000 |
MARCH 7, 2000
|
MARCH 7, 2000 |
|
|
MARCH 7, 2000
|
JULY 22, 2000
|
|
|
JULY 22, 2000
|
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
|
|
|
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 26, 2001 |
FEBRUARY 13 2003 |
|
|
MARCH 13, 2003 |
APRIL 28, 2003 |
|
|
MARCH 13, 2003 |
MARCH 16, 2002 |
JUNE 9, 2003 |
JUNE 9, 2003 |
MARCH 20, 2004 |
MARCH 20, 2004 |
MARCH 20, 2004 |
![]()
MARCH 20, 2004 |
|
|
![]() JUNE 5, 2004 |
![]()
JUNE 5, 2004 |
|
|
JUNE 5, 2004 |
JULY 7, 2004 |
MARCH 19, 2005 |
MARCH 19, 2005 |
![]()
MARCH 19, 2005 |
|
|
|
MARCH 19, 2005 |
MARCH 19, 2005 |
MARCH 19, 2005 |
MARCH 19, 2005 |
MARCH 19, 2005 |
MARCH 19, 2005 |
JUNE 4, 2005 |
JUNE 4, 2005 |
![]()
JULY 23, 2005 |
AUGUST 19, 2005 |
|
|
AUGUST 19, 2005 |
JAN 2, 2006 |
JAN 2, 2006 |
JAN 2, 2006 |
|
|
JAN 2, 2006 |
JAN 2, 2006 |
JAN 2, 2006 |
JAN 2, 2006 |
|
|
JAN 2, 2006 |
JAN 2, 2006 |
FEB 16, 2006 |
FEB 16, 2006 |
|
|
|
|
FEB 27, 2006 |
FEB 27, 2006 |
|
|
MARCH, 2006 |
MARCH, 2006 |
|
|
MARCH, 2006 |
![]()
MARCH, 2006 |
|
|
MARCH, 2006 |
MARCH, 2006 |
|
|
MARCH, 2006 |
MARCH, 2006 |
|
|
|
|
MOVING DAY The Mid Atlantic Air Museum reaches a milestone on the road to fully restoring and returning its now famous Northrop P-61 “Black Widow” restoration project to airworthy condition. During the last weekend in April, Museum crews move the three major components from the restoration shop where they have taken shape since 1991. The left and right inner wing or engine nacelles were mated with the fuselage, after which the landing gear was lowered and locked for the first time since January, 1945. |
|
![]()
APRIL 28, 2006 |
|
|
|
APRIL 28, 2006 |
![]()
APRIL 28, 2006 |
|
|
![]()
APRIL 28, 2006 |
![]()
APRIL 28, 2006 |
|
|
![]()
APRIL 28, 2006 |
![]()
APRIL 28, 2006 |
|
|
APRIL 28, 2006 |
APRIL 28, 2006 |
APRIL 28, 2006 |
![]()
APRIL 28, 2006 |
|
|
![]()
APRIL 28, 2006 |
![]()
APRIL 28, 2006 |
|
|
APRIL 29, 2006 |
|
|
|
![]()
APRIL 29, 2006 |
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
APRIL 29, 2006 |
APRIL 29, 2006 |
|
|
APRIL 29, 2006 |
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
|
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
APRIL 29, 2006
|
APRIL 29, 2006 |
|
|
APRIL 29, 2006 |
APRIL 29, 2006 |
|
|
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
![]()
APRIL 29, 2006 |
![]()
APRIL 29, 2006 |
|
|
IN THE HANGAR, AS IN THE RESTORATION SHOP, THE WORK GOES ON | |
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]() |
![]() |
AUGUST 25, 2006 WING FAIRINGS |
|
|
|
![]()
AUGUST 25, 2006 |
![]()
AUGUST 25, 2006 |
|
|
![]() |
![]() |
OCTOBER 31, 2006 ONE OF THE TAIL BOOMS IN A JIG, CLEANED AND READY FOR DENT REPAIRS |
|
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]()
OCTOBER 31, 2006
|
![]()
OCTOBER 31, 2006
|
|
|
![]() |
![]() |
![]() |
![]() |
OCTOBER 31, 2006 ALL THE PLEXIGLAS WINDOWS ARE INSTALLED |
|
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]() |
![]() |
OCTOBER 31, 2006 DON YOUNGBLOOD SHOWS HYDRAULIC LINES & TRIAL FITS AN ARMOR PLATE |
|
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]()
OCTOBER 31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]() |
![]() |
![]() |
![]() |
OCTOBER 31, 2006 THE RADAR OPERATOR'S COMPARTMENT IN THE REAR OF THE CREW POD HAS ITS ENTRY HATCH AND LADDER INSTALLED, ALONG WITH ITS WARTIME RADIOS. |
|
|
|
![]() |
![]() |
![]() |
![]() |
OCTOBER 31, 2006 THE COCKPIT: THE FLAP CONTROL LEVER IS ABOVE THE THROTTLE QUADRANT. THE OXYGEN REGULATOR IS ON THE RIGHT SIDE AND ITS GAUGES FORWARD OF IT. IN THE LOWER COCKPIT SHOT, AUTO-PILOT HYDRAULIC CONTROLS ARE ON THE LOWER RIGHT AND THE RED FUEL TANK SELECTOR LEVERS ARE ON THE LEFT. |
|
|
|
![]() OCTOBER
31, 2006 |
![]()
OCTOBER 31, 2006 |
|
|
![]() |
![]() |
JANUARY 3, 2007 THE GUNNERS SEAT WITH THE GUN CONTROL HANDLES IN THE SHOP |
|
|
|
![]()
JANUARY 3, 2007 |
![]()
JANUARY 3, 2007 |
|
|
![]()
JANUARY 3, 2007 |
![]()
JANUARY 3, 2007 |
|
|
![]() |
![]() |
![]() |
![]() |
FEBRUARY 22, 2007 WORK IS UNDERWAY ON THE VERTICAL TAIL ASSEMBLIES |
|
|
|
![]() P-61 PILOT CAPTAIN ROBERT G. BOLINDER POSES WITH THE P-61 MODEL UNDER THE REAL THING AT MAAM'S 17TH ANNUAL WORLD WAR II WEEKEND, JUNE 1-3, 2007 |
|
|
|
![]() |
![]() |
P-61 AND ITS LITTLE SISTER ON DISPLAY IN THE HANGAR AT MAAM'S 17TH ANNUAL WORLD WAR II WEEKEND, JUNE 1-3, 2007 |
|
|
|
![]()
JUNE 28, 2007 |
![]()
JUNE 28, 2007 |
|
|
![]()
JULY 9, 2007 |
|
|
|
![]()
JULY 9, 2007 |
![]()
JULY 9, 2007 |
|
|
![]()
JULY 9, 2007 |
![]()
JULY 9, 2007 |
|
|
![]()
SEPTEMBER 18, 2007 |
![]()
SEPTEMBER 18, 2007 |
|
|
![]()
SEPTEMBER 18, 2007 |
![]()
SEPTEMBER 18, 2007 |
|
|
![]()
SEPTEMBER 18, 2007 |
![]()
SEPTEMBER 18, 2007 |
|
|
![]()
SEPTEMBER 18, 2007 |
![]()
DECEMBER 5, 2007 |
|
|
![]()
DECEMBER 5, 2007 |
![]()
DECEMBER 5, 2007 |
|
|
![]()
DECEMBER 5, 2007 |
![]()
DECEMBER 5, 2007 |
|
|
![]()
DECEMBER 5, 2007 |
![]()
DECEMBER 5, 2007 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
APRIL 26, 2008 |
|
|
![]()
APRIL 26, 2008 |
![]()
SEPTEMBER 2, 2008 |
|
|
![]() SEPTEMBER 2, 2008 COMPLETED RIGHT VERTICAL FIN IN THE HANGAR |
![]()
SEPTEMBER 2, 2008 |
|
|
![]()
SEPTEMBER 3, 2008 |
![]()
SEPTEMBER 3, 2008 |
|
|
![]()
SEPTEMBER 3, 2008 |
![]()
SEPTEMBER 3, 2008 |
|
|
![]()
FEBRUARY 13,
2009 |
![]()
FEBRUARY 13,
2009 |
|
|
![]()
FEBRUARY 13,
2009 |
![]()
FEBRUARY 13,
2009 |
|
|
![]()
FEBRUARY 13,
2009 |
![]()
FEBRUARY 13,
2009 |
|
|
![]()
FEBRUARY 13,
2009 |
![]()
FEBRUARY 13,
2009 |
|
|
![]()
FEBRUARY 13,
2009 |
![]()
FEBRUARY 13,
2009 |
|
|
![]()
FEBRUARY 13,
2009 |
MARCH 5, 2009 |
|
|
![]()
MARCH 9, 2009 |
![]()
MARCH 9, 2009 |
|
|
![]()
APRIL 23, 2009 |
![]()
APRIL 23, 2009 |
|
|
![]()
APRIL 23, 2009 |
![]()
AUGUST 26,
2009 |
|
|
![]()
AUGUST 26,
2009 |
![]()
AUGUST 26,
2009 |
|
|
![]()
AUGUST 26,
2009 |
![]()
AUGUST 26,
2009 |
|
|
![]()
AUGUST 26,
2009 |
![]()
AUGUST 26,
2009 |
|
|
![]()
AUGUST 26,
2009 |
![]()
AUGUST 26,
2009 |
|
|
![]()
AUGUST 26,
2009 |
![]()
AUGUST 26,
2009 |
|
|
DECEMBER 8,
2009 |
DECEMBER 8,
2009 |
|
|
![]() |
![]() |
![]() |
![]() |
MARCH 5, 2010 THE ORIGINAL ELEVATOR FRAME STANDS BENEATH THE FINISHED HORIZONTAL STABILIZER |
|
|
|
![]() |
![]() |
MARCH 5, 2010 |
APRIL 4, 2010 |
|
|
|
|
MAY 13, 2010 THE LEFT BOOM IS MOVED INTO POSITION |
MAY 13, 2010 TWEAKING THE LEFT BOOM POSITION |
|
|
|
|
MAY 13, 2010 GENE STRINE INSPECTS THE JOIN |
MAY 13, 2010 |
|
|
|
|
MAY 13, 2010 RIGHT BOOM IN PLACE |
MAY 13, 2010 |
|
|
|
|
MAY 13, 2010 LUKE JONES WORKS INSIDE THE BOOM |
|
|
|
![]() |
![]() |
![]() |
![]() |
MAY 23, 2010
THE VERTICAL
AND HORIZONTAL STABILIZERS ARE MATED TO THE TAIL BOOMS AS THE P-61 IS
READIED FOR ROLL-OUT AT WORLD WAR II WEEKEND |
|
![]() |
![]() |
JUNE 2, 2010 THE BLACK WIDOW, WITH TAIL BOOMS, AND VERTICAL AND HORIZONTAL STABILIZERS ATTACHED, IS PULLED OUT OF THE HANGAR BY RUSS STRINE AND HIS GROUND CREW. |
|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
JUNE 2, 2010
THE BLACK
WIDOW TAKES ITS PLACE UNDER THE TENT FOR DISPLAY AT THE 20TH ANNIVERSARY
WORLD WAR II WEEKEND |
|
![]() |
|
JUNE 3, 2010 THE AUTHORS OF "FORGOTTEN WIDOW" AUTOGRAPH COPIES OF THE NEW BOOK AT WORLD WAR II WEEKEND. FROM LEFT TO RIGHT, SHARON WELLS WAGNER, GENE STRINE, STEVE WAGNER, AND RUSS STRINE.
|
|
|
|
OCTOBER
25, 2010
THE P-61 WITH HORIZONTAL STABILIZER,
VERTICAL STABILIZER AND TAIL BOOMS INSTALLED. |
JUNE 3, 2010 PROGRESS REMAINS STEADY EACH WEEK. HERE, FUSELAGE WIRING HARNESSES ARE BEING INSTALLED.
|
|
|
|
|
JUNE 3, 2010
A P-61
R2800-65 QEC ENGINE IS BEING READIED FOR TEMPORARY INSTALLATION ON THE
AIRCRAFT. |
JUNE 3, 2010
THE P-61 IS A BIG ATTRACTION AND AN IMPRESSIVE SIGHT AS IT SITS IN THE MUSEUM DISPLAY HANGAR. VISITORS CAN WATCH AS THE ACTUAL RESTORATION PROCEEDS IN PLAIN VIEW. |
|
|
|
|
JUNE 3, 2010
THE P-61 ELEVATOR DRAWS NEARER TO COMPLETION. EACH RIB HAS FACE PLATES SPOT WELDED TO ITS FLANGES. THESE PLATES HOLD THE CLIPS WHICH WILL ULTIMATELY ATTACH THE FABRIC COVERING. |
JUNE 3, 2010 THE PROCESS OF FITTING AND DRILLING THE NEW SHEET METAL FOR THE ELEVATOR'S LEADING EDGE BEGAN WITHIN HOURS AFTER THIS PHOTO WAS TAKEN. |
|
|
|
|
MARCH 23, 2011 Wiring installation proceeds on the P-61 |
MARCH 23, 2011 Cowl-flap ring, ready for installation on the P-61 |
|
|
|
|
MARCH 23, 2011 One of the P-61's Pratt & Whitney R-2800-65 Double Wasp 18-Cylinder engines stands ready for installation. |
|
|
|
While the recovery and restoration of MAAM’s rare P-61B 42-39445 has been a daunting task, there have been some extremely challenging tasks within the project itself. Rewiring it is one of those! We’re trying to do it right, however it is super time consuming to do so. When we say “right” not only do we mean that all circuits are returned to what they once were, we also mean that we have utilized all of the correct cannon plugs, junction blocks, relays etc. In the majority of cases you just can’t go to the parts store and pick up what you need. Some items Northrop had made especially for the P-61. In a number of cases we have had to make the part, or a piece of a part or connector. We are lucky to have an extraordinary machine shop and a seasoned machinist with experience in the microprocessor industry who is able to reverse engineer what we need to have made. While we do have the P-61 drawings on 17 reels of microfilm, that does not include parts Northrop procured from vendor suppliers – which included nearly all electrical items! So please, enjoy the newly posted photos of the P-61 electrical installation, but be patient – there’s obviously still a lot more electrical work to do.
|
|
OCTOBER 23, 2011 |
|
|
|
wiring harnesses going into right side pilot's compartment | wiring harnesses and connectors on right side turret compartment |
|
|
|
|
the SCR 720 radar antenna sitting on the electrical bench | turret compartment buss bar junction box wiring |
|
|
|
|
recently refinished gunner's cockpit seat | recently acquired night binoculars |
|
|
|
|
pilot's end of night binoculars | front side of night binoculars |
|
|
|
|
radar operator's seat installed in entry position | power junction box and one of the turret amplidynes |
|
|
|
|
pilot's night binocular mounting frame | pilot's lower instrument panel and wiring |
|
|
|
|
pilot's generator control panel | inboard side left-hand wheel well wiring |
|
|
|
|
more connectors and harnesses in lower right turret compartment near lower rear spar | left-hand nacelle battery wiring , relay, and AN style battery connector |
|
|
|
|
left hand side pilot's compartment wiring installation | left hand nacelle firewall and engine wiring harnesses |
|
|
|
|
heater installation and wiring in right rear gunner's cockpit | gun turret control box and shielded wire harnesses |
|
|
|
|
general view looking aft from gunners cockpit toward radio operators compartment | junction box and wiring right upper turret compartment |
|
|
|
|
external power receptacle and wiring in left-hand aft wheel well | circuit breaker panel on pilot's right side |
|
|
|
|
a view of the electrical shop bench with enlarged electrical drawing spread across it | another view of the electrical bench |
|
|
|
|
another right side turret compartment junction box | radar wiring harness in left-hand lower fuselage, must be installed before skin can be riveted in place |
SEPTEMBER 20, 2012 |
|
![]() |
![]() |
Pappy Strine, shown here bucking rivets on the P-61 elevator. | Luke Jones and Pappy Strine install rivets on the elevator leading edge. |
|
|
![]() |
![]() |
When the elevator is finally finished the fixture will be modified and reused for rebuilding the wings. | One of the drop tanks. |
|
|
![]() |
![]() |
Another one of the drop tanks awaits restoration. | Wiring and hydraulics in the right rear of the turret compartment. The fuselage carry thru spars can be seen at right. |
|
|
![]() |
![]() |
The gun compartment showing the two lower 20mm cannons and LH upper gun | A view of the cannons. |
|
|
![]() |
![]() |
View of the area behind the instrument panel with the armor plate removed | Nose gear wiring to control switches and taxi lights |
|
|
![]() |
![]() |
Gunner's turret control box is mounted on the RH gunners cockpit wall. | The landing gear selector handle is mounted left of center on the pilot's sub panel |
|
|
![]() |
![]() |
The flap control handle on the left cockpit wall | Bail out bell on LH side between pilot and gunner |
|
|
![]() |
![]() |
Ammeter s and circuit breaker box on RH pilots wall. | RH gunners folding armor plate. Cockpit heater is installed in the right rear corner. |
|
|
![]() |
![]() |
Gunners LH folding armor plate. | Propeller switch box ready for installation on the left cockpit wall. |
|
|
![]() |
![]() |
he throttle quadrant awaits being strung once the wiring is in place. Mounts for elevator, rudder, and aileron trim wheels. | More wiring at the instrument panel. Completed harnesses have cannon plugs installed which are wrapped in plastic. |
|
|
![]() |
![]() |
ilot's instrument panel. The bok to the left contains the main switch panel. Directly in the center is the autopilot rack. | The voltage regulator box installed on the bulkhead at the aft end of the gunner's compartment. |
|
|
![]() |
![]() |
RH turret compartment wiring. Once each bundle is complete it will be combed out and laced in place | Wiring on the LH turret compartment buss is in process. |
|
|
![]() |
![]() |
Wiring harness inside the lower right fuselage. This is mostly radar wiring. | Right hand nose gear door being fitted |
|
|
![]() |
|
Fitting the new leading edge skin to the elevator | |
|
|
AUGUST 11, 2013 | |
![]() |
![]() |
Left side gunners movable armor plate | Night binoculars in their stored position along the left pilot's window |
|
|
![]() |
![]() |
Left side lower fuselage wiring harness forward of gun bay | Completed elevator structure |
|
|
![]() |
![]() |
Pilot's electrical panel and electrical harness | Ongoing wiring on the right side of the turret compartment |
|
|
![]() |
![]() |
Ongoing wiring on the lower pilot's instrument panel | Nose bulkhead forward of instrument panel behind armor plate |
|
|
![]() |
![]() |
Ignition light panel, O2 panel air pressure and autopilot hydraulic pressure gauges on RH side of pilot's compartment | Pilot's view of the rare night binoculars |
|
|
![]() |
![]() |
Right hand wing root pulled out of storage in preparation of rebuild | Right side of gunner's compartment wiring harness |
|
|
![]() |
![]() |
Right wing and spoilers | Right wing leading edge shows where Ironwood trees were hit |
|
|
![]() |
![]() |
Right wing outboard showing aileron mount and spoilers | Right wing root and Ironwood tree damage |
|
|
![]() |
![]() |
Sliding track for pilot's night binoculars | Ongoing wiring harness' on left side of cockpit |
|
|
![]() |
![]() |
View into the R.O.'s compartment from the aft boarding ladder | View into the RO's compartment from the boarding ladder |
|
|
![]() |
![]() |
View of nose wheel well and forward entry area from gunners compartment | View of pilot's night binoculars in stowed position looking to left rear from pilots seat area |
|
|
![]() |
![]() |
Voltage regulator panel at aft end of gunners compartment | The RH wing disassembly begins |
|
|
![]() |
![]() |
RH wing of the P-61 being disassembled. | The leading edge and damage from hitting multiple Ironwood trees |
|
|
![]() |
![]() |
The trailing edge and outboard spoilers (inboard spoiler removed). | View of the aft side of the inboard spoiler. |
|
|
![]() |
![]() |
Volunteer cleaning 40 years worth of debris out of the oil tank and oil cooler bays | Inboard spoiler section removed. Spoilers are .250 thick magnesium alloy plate. |
|
|
![]() |
![]() |
Cleaning out the oil tank bay with the self sealing oil tank removed. | Workman is drilling off the last outboard skin panel on the wing's top side. |
|
|
![]() |
![]() |
The spoilers, inboard in foreground, outboard sections still in wing in backround. | The small 22 gallon self sealing oil tank shown here after being removed. |
|
|
![]() |
![]() |
RH Nose Landing Gear Door. Completed and Ready for Installation | Lots of progress in just two weeks. The entire trailing edge section has been removed as well as the top center wing skins. |
|
|
MAAM'S P-61 "BLACK WIDOW" ON DISPLAY AT OUR 2014 WORLD WAR II WEEKEND | |
|
|
![]() |
![]() |
|
|
![]() |
![]() |
|
|
![]() |
![]() |
|
|
![]() |
|
APRIL 30, 2015 |
|
![]() |
![]() |
Wing trailing edge section. | Wing rib forms. |
|
|
![]() |
![]() |
Propeller spinner fairings. |
New nose section wing ribs. |
|
|
![]() |
![]() |
New spar web section. |
New spar web section. |
|
|
![]() |
![]() |
Wing trailing edge section. | Wing rib forms. |
|
|
![]() |
![]() |
Propeller spinner fairings. |
New nose section wing ribs. |
|
|
![]() |
![]() |
New spar web section. |
New spar web section. |
|
|
JUNE 28, 2016 | |
|
|
Right wing oil cooler scoop in process of forming and fitting. | Right wing trailing edge parts. |
|
|
|
|
Right wing trailing edge. | More right wing trailing edge and flap well. |
|
|
|
|
Right rear wing spar in fixture | Right rear wing spar build-up. |
|
|
|
|
Curtiss Electric propeller parts prior to assembly. |
Curtiss Electric propeller blades after black anodizing process. |
|
|
|
|
Curtiss Electric propeller assembly |
|
|
|
JANUARY 30, 2017 | |
With the amount of work remaining to be accomplished and the variables involved, no completion date can be set at this time. The P-61 project is worked on daily by a full-time professional restoration staff. When a completion date comes within a predictable timeframe, it will be promptly posted on this website. |
|
|
|
The Museum's members and its many friends and supporters are determined to see this fascinating plane restored to flying status. We ask all of you who share their love of aviation history and would like to see this unique aircraft fly again to help with a donation toward its restoration. |
|
![]() As with the Black Widow itself, we are constantly in the process of rebuilding and updating the Widow's Web. As work progresses on the aircraft there will be new photos and features about our P-61 Restoration Project. Please check back in soon, and don't forget to hit your browser's refresh button to see what's new since your last virtual visit. |
|
This website is the intellectual property and © Copyright of Mid-Atlantic Air Museum, 2018. All rights reserved. No reproduction, distribution, or transmission of the material on this website is permitted without the expressed written permission of the Mid-Atlantic Air Museum.
web page developer and webmaster Bill Rambow